E-ISSN: 2963-3699
P-ISSN: 2964-0121
Homepage: Homepage: https://return.publikasikupublisher.com
This work is licensed under CC BY-SA 4.0
THE USE OF TEMPORARY TOWERS TO OPTIMIZE THE COMPLETION
OF RECONDUCTORING AND TOWER REPLACEMENT OF 150 KV HIGH
VOLTAGE OVERHEAD LINES (SUTT)
Muhammad Iqbal
Sepuluh Nopember Institute of Technology, Surabaya, Indonesia
ABSTRACT
Transmission lines play an important role in the successful and stable operation and distribution of power
grids both for power evacuation from power plants and as a link from one Substation to another. The
construction of new transmission lines as a form of meeting high electricity needs in the current era of
Globalization has many obstacles, both in terms of rejection from residents, expensive licensing
arrangements, and very expensive investment costs. Reconductoring is one of the methods of increasing
transmission capacity at minimum cost with an adequate level of quality and reliability. Reconductoring
is the best solution today to increase conductor conducting capacity with the least investment and get
maximum economic efficiency. However, considering that reconductoring is an addition of transmission
capacity using old or existing lines and also requires tower replacement, so an outage with a long duration
is needed which is feared to have an impact on system reliability. Therefore, the use of emergency towers
is believed to be a solution to shorten the blackout time. Emergency towers are used as tools in
reconductor work and tower replacement. A study was conducted by calculating the Cost Budget Plan
(RAB) and schedule analysis using the Microsoft Project Application to determine the comparison of
the duration of time needed to complete reconductoring work and tower replacement between using an
emergency tower and without an emergency tower. From the time schedule made, it will be known which
work method uses a shorter duration of time so that it can save or speed up the blackout time. This study
is expected to produce a shorter schedule of reconductoring and tower replacement work using
temporary/emergency towers and with a smaller RAB compared to Total Operating Costs so as to
shorten the duration of the outage time at an efficient cost.
Keywords: Rekonduktoring, Tower Emergency, Speed up work
INTRODUCTION
PT PLN (Persero) is a company engaged in electricity, one of its activities is to build
electricity infrastructure, manage network construction activities, supervise construction and
carry out construction administration processes by acting as the owner of work (owner) and
Director of Work for PT PLN (Persero) Head Office contracts by producing quality networks and
ready to operate with processes implementation of development based on cost, quality and on
time (Aldi et al., 2022; Maidin et al., 2022).
150 kV Reconductoring Work is one of the electricity network projects built by PLN which
is one of the Government Programs in building national electricity. The Sukatani New-Sukatani
150 kV SUTT Reconductor Work is needed to be able to evacuate energy production from the
plant to the load, especially with the plan to build a Java 1 2x800 MW PLTGU with a radial
connection from GITET Cibatu Baru II / Sukatani and increase the reliability of industrial center
supply, especially to supply industrial estates on the north side of Karawang. The existing
conductor of SUTT 150 kV Sukatani New-Sukatani currently still uses Dove 1x298 mm2 with a
capacity of 600 A. This will certainly be a very crucial factor because this section will be used as
a power evacuation outlet from GITET Sukatani through GIS 150 kV Sukatani New towards
Sukatani-TX-Bekasi-Kosambi Baru so it must be reconductord because it requires a larger
conducting capacity (Kishore & Singal, 2014).
In order to support the plan of the 150 kV Sukatani Ne-Kosambi Baru SUTT Reconductor
work, it is necessary to carry out the 150 kV Sukatani New-Sukatani SUTT Reconductor work
first so that bottle necking does not occur on this path when evacuating power from PLTGU Jawa
1 2x800 MW.
The Use of Temporary Towers to Optimize The Completion of Reconductoring and Tower Replacement
of 150 Kv High Voltage Overhead Lines (SUTT)
650 Return: Study of Economic And Business Management, Vol 2 (7), Juuly 2023
Construction work on the SUTT 150 kV Kosambi Baru-Sukatani reconductor as a
reinforcement of the GITET 500 kV Sukatani power evacuation outlet which will operate in 2022
(PT PLN (Persero) Unit Induk Pusat Pengatur Beban, 2019).
The configuration of GITET 500 kV Sukatani is to cut 2 circuits of SUTET 500 kV Muara
Tawar Cibatu. GITET 500 kV Sukatani New outlet is GIS 150 kV Sukatani New whose
configuration plan cuts 2 circuits SUTT 150 kV Bekasi-Kosambi Baru (PT PLN (Persero) Unit
Induk Pusat Pengatur Beban, 2019).
The Reconductor Work of the 150 kV Sukatani New-Sukatani SUTT is targeted to be
completed in December 2022 considering that the 150 kV Sukatani New GIS will be operated at
the end of 2022 so that the evacuation of power from the Java 1 2x800 MW PLTGU through the
500 kV Sukatani GITET and the 150 kV Sukatani New GIS Step Down will be optimal.
This research will discuss the use of emergency tower tools to accelerate the completion of
the Sukatani New-Sukatani New-Sukatani 150 kV SUTT Reconductoring work compared to not
using emergency towers in order to pursue operating targets at the end of 2022 in accordance with
the Key Performance Indicator (KPI) targets set by management. Given that the tower on the line
is very old and has a conductor with a small capacity that is no longer suitable with the current
technological capacity, so the project is highly recommended by users to immediately reconductor
and replace the tower. In addition, this line is a crucial line that is currently very reliable to supply
electricity from Sukatani New to Sukatani and Kosambi Baru where when this work is carried
out, blackouts with too long a duration of time are not allowed (Mbuli et al., 2019; Reed et al.,
2020).
This reconductoring project is very closely related to blackouts so that in order to anticipate
and minimize the duration of long work time, an emergency tower method is needed so that it can
reduce the duration of time. So it is expected that the outage of the line will not be too long which
is feared to disrupt the need for electricity supply on the line.
RESEARCH METHOD
Data collection in this study was carried out by collecting information from a 150 kV
transmission reconductoring project at PT PLN (Persero) which is very useful for evaluating
overall time and cost optimization (Vadivel, 2017). This study requires several designs as
direction (guidance) in data collection so that the data obtained there is no doubt about its validity
and reality, as follows: Design Criteria for determining the type of conductor, Parameter Design,
namely by applying Operations Management such as human resources, cost budgets, conductor
materials, machines, methods; Experiment Design (Teniwut, 2022).
Data sources in this study use primary data, with field surveys, holding Group Discussions
(FGDs) to determine Decision Criteria, Cross Checking, Validity and Reliability. Secondary data
is data obtained from the results of collecting various previously existing data that will be used
by researchers to complement primary data that has been obtained, including contract document
books, Cost Budget Plans (RAB), data from other agencies such as contractors, construction
supervision consultants and other data related to the research topic. The variables that greatly
influence the optimization of project implementation time and cost are time variables and cost
variables (Kopsidas & Rowland, 2009).
Data processing, steps as follows: Create and Calculate Budget Plan (RAB) Contract
Amendment; Create a project comparison time schedule; Calculating the Cost Comparison Value
between the Amendment Budget and Total Operating Costs.
Data Analysis, After data processing is carried out both starting from making and
calculating the cost budget plan (RAB) for contract amendments, Primary Data, and Secondary
Data, the output is obtained in the form of comparative data, including: Cost Budget Plan Value
(RAB), and Time Schedule for the implementation of work, then these data are analyzed as a
reference in choosing which method is more effective and efficient in completing projects in
Research this time.
The Use of Temporary Towers to Optimize The Completion of Reconductoring and Tower Replacement
of 150 Kv High Voltage Overhead Lines (SUTT)
Return: Study of Management, Economic and Bussines, Vol. 2 (7), July 2023
651
Drawing conclusions and suggestions, The last step includes the analysis obtained from the
results of data processing carried out during the research and the results of analysis and discussion
can be concluded as the results of the research as a whole.
RESULT AND DISCUSSION
Field Data
The project reviewed in this study is one of the Network Transmission Reconductoring
projects at PT PLN (Persero) SUTT 150 kV Sukatani New towards Sukatani 4-CIRCUIT OHL 2
X TACSR 410/67 mm2 (Krishnasamy et al., 1981; Riba et al., 2020; Schweiner et al., 2003).
The Cost Budget Plan and time schedule for the project can be seen in the following
explanation.
Data Analysis
This analysis will explain how the Microsoft Project program can be used to speed up
outage times with variations using Temporary/emergency Tower, with the following stages :
1. Drawing up a project schedule and cost plan (Wale et al., 2015),
2. Acceleration of project blackout time with variations using Tower Emergency. Then the
result of accelerating the blackout time with variations using Tower Emergency is in the
form of changes in costs before and after using Tower Emergency compared to the duration
of the outage.
Creating Project Schedules and Costs
The steps in creating a project schedule by using the Microsoft Project program can be
done as follows (Harefa, 2021):
1. Open a new worksheet Click the Start button > Microsoft Office > Programs > Microsoft
Project
2. Enter the project's effective date.Enable the Project > Project Information menu. In the
Project Information dialog box, Schedule From : Project Start Date is selected, then enter
the project's effective date, which is August 1, 2022 in the Start Date box. These steps can
be seen in Figure 1 below.
Figure 1
Enter the Project's Effective Date date
3. Create a work schedule to determine working days and hours. This project uses a typical
calendar workday of 7 working days per week with 8 hours of work per day. Enter the data
The Use of Temporary Towers to Optimize The Completion of Reconductoring and Tower Replacement
of 150 Kv High Voltage Overhead Lines (SUTT)
652 Return: Study of Economic And Business Management, Vol 2 (7), Juuly 2023
on the number of working days and hours in the Microsoft Project program, first click the
Tools menu > Change Working Time > Work Weeks > Details then in the select day(s) box
select all days then select Set day(s) to these specific working times. Next, enter the working
hours in the Form boxes: 08.00 To: 12.00 and Form: 13.00 To: 17.00 > OK. Then on the
Work Weeks view select Options, fill in the data in the Default start time box: 08.00; Default
end time: 17.00; Hours per day: 8.00; Hours per week: 56.00; and Days per month: 30.
Langkah-langkah tersebut dapat dilihat pada Gambar 2, Gambar 3, dan Gambar 4 berikut
ini:
Figure 2
Enter workdays and working hours
Figure 3
working hours per day, working hours per week, and working days per month
4. After all project preparation and determination of the calendar of working days and hours,
the next step is to compile data on project activities consisting of all work items that form
the sequence of the entire series of activities. Work items in project activities are performed
The Use of Temporary Towers to Optimize The Completion of Reconductoring and Tower Replacement
of 150 Kv High Voltage Overhead Lines (SUTT)
Return: Study of Management, Economic and Bussines, Vol. 2 (7), July 2023
653
5. in the following steps: From the View menu> click Gantt Chart > in the Task Name field,
enter the name of the entire series of work activities, in the Duration field, enter the time
duration of each job. Then create relationships between work items entered in the
Predecessors column, after the Task Name, Duration, Predecessors columns have all been
filled then the Start and Finish columns will be automatically filled with the right display
showing the results in the form of a Gantt Chart according to the data entered. The results
can be seen in Figure 4 below.
Figure 4
Work Item Creation with Gantt Chart view
Acceleration of Blackout Time with Variations Using Tower Emergency
The acceleration of project blackout time with variations using Tower Emergency is carried
out by filling in Tower Emeregency data which is then compared with normal conditions, namely
conditions before acceleration. The steps at this stage include::
1. In the Gantt Chart view, add Tower Emergency work items and data
2. Enter the duration of a work item as planned
Figure 5
Enter the Effective Date of the Project by using the Temporary Tower
The Use of Temporary Towers to Optimize The Completion of Reconductoring and Tower Replacement
of 150 Kv High Voltage Overhead Lines (SUTT)
654 Return: Study of Economic And Business Management, Vol 2 (7), Juuly 2023
3. Entering project activity data using Tower Emergency
Figure 6
Creation of Work Items with Temporary Tower with Gantt Chart display
Discussion
Project Acceleration to Reduce Outage Time Duration
Following up on a request from the Load Control Unit that in order to maintain the
reliability of electricity supply in the Java system, it is necessary to accelerate work related to the
blackout of existing lines. In this research, of course, it can be done using the Temporary Tower
tool (Ahmed & Saqib, 2020; Ines & Ammar, 2020).
Shortening the duration of outage time is the main point in the implementation of this
reconductor project. With a relatively shorter duration of blackouts, it can maintain the reliability
of the electricity system on the island of Java. The following is a comparison of the calculation
of the duration of the outage time between without using a temporary tower and using a temporary
tower.
Acceleration Measures
The acceleration steps in the reconductoring project plan are described as follows (Rashmi et al.,
2017; Reddy & Chatterjee, 2016).
1. Without Using Temporary Tower
Conditions if the reconductor work is carried out without using a temporary tower, then the
blackout time of this reconductor project is 148 days. These activities cannot be accelerated,
because the system must be completely extinguished during erection work T.04 and Uprating
work of existing Towers T.76, 77 and 78 in the direction of Sukatani.
2. Working Method Without Using Tower Emergency. Stages of Work Implementation :
a) 148-day blackout permit for erection work T.04 up to uprating work T.76, 77, and 78
b) Mobilization of Manpower and Equipment to tower point T.04
c) Work began with dismantling conductors, fittings & accessories, towers, up to the
foundation of the existing tower footprint (T.76, 77, and 78)
d) After the existing tower dismantling work until the foundation is completed, the
foundation material curtain work and the new T.76, 77, and 78 foundation work continue
e) Continued curtain and erect tower work T.76, 77, and 78 after a concrete curing period
of ± 8 days
f) After the erect tower work was completed, the work continued to pull Line 1 conductors
from T.04 to T.75E
g) After the Line 1 conductor has been installed, continue to draw the Line 2 conductor
Line
h) Finished the work of pulling Line 1 and 2 conductors, continued the implementation of
Rele Line Diff installation work at GI Lawan, then carried out Individual test &;
The Use of Temporary Towers to Optimize The Completion of Reconductoring and Tower Replacement
of 150 Kv High Voltage Overhead Lines (SUTT)
Return: Study of Management, Economic and Bussines, Vol. 2 (7), July 2023
655
Function work, SAS Integration and Testing &; Commisioning at GI Sukatani Gobel
and GIS Sukatani New
i) After the Testing & Commissioning Work is completed, the Point to Point, Stability Line
Diff and Intertrip exams continue
j) Continued issuance of RLB and Energize direction Sukatani Gobel.
3. Dengan menggunakan Tower Emergency
The acceleration step in question is to shorten the blackout time in the work produced
by the previous stage, which is the normal stage. The calculation of acceleration needs using
the Temporary Tower inputted under normal conditions led to a reduction in project blackout
time from 148 days to 16 days. This acceleration caused the project cost requirement to
experience an additional cost of Rp 1,872,217,454 from the original plan cost.
4. Working method using Temporary Tower
Stages of Work Implementation :
a) Mobilization of Manpower and Equipment to the point tower T.04
b) Blackout permit for 14 days from Erection work to Cut joint work
c) Complete erection work at T.04 and perform final check
d) Line up conductor from direction T.03 to T.04 3 phase up line direction Bekasi and
continued 3 phase down direction sukatani gobel.
e) Thorough checking of the strength of tower members, tower body and cross arm as well
as bolt fittings accessories
f) Ensuring the strength condition of the T.79E to avoid chronic damage
g) If the condition of T.79 is still strong, the cut join work can be started by unclamping on
T.79 and installing the roll
h) The work of erecting the Temporary Tower along with the work of Mobilizing Manpower
and Equipment to the tower point T.04
i) Established 3 temporary tower points with sekur reinforcement
j) Install insulators and accessories at the end of the crossarm temporary tower and roll
mounted
k) Carrying out a new cable withdrawal 2xTACSR 410 in the Temporary Tower from T.75E
to T.04
l) After erection T.04 is complete, new cables are clamped in T.04 and in T.75E
m) The conductor in T.04 will be cut, which is from the direction of Sukatani line, the
temporary tower is placed in the lower 3 phase crossarms and the one from Bekasi
direction is in the upper 3 phase crossarms
n) Carry out Rele Line Diff installation work at GI Lawan, then do Individual test &;
Function and Testing &; Commisioning work
o) After the Testing & Commissioning Work is completed, the Point to Point, Stability Line
Diff and Intertrip exams continue
p) Followed by the issuance of RLB and Energize Line 1 in the direction of Sukatan
q) After the work of cutting the connection of T.04 and Energize Line 1 in the direction of
Sukatani Gobel, the work on uprating the existing towers T.76, 77, and 78 can begin
r) Pekerjaan dimulai dengan dismantling konduktor, fitting & accessories, tower, sampai
dengan pondasi tapak tower eksisting
s) After the existing tower dismantling work until the foundation is completed, the new T.76,
77, and 78 foundation work continues
t) Continued curtain and erect tower work T.76, 77, and 78 after a concrete curing period of
± 8 days
u) After the erect tower work was completed, the conductor withdrawal work continued from
T.04 to T.75
v) Furthermore, the permit went out for 2 days for the transfer of conductors from the
temporary tower to towers T.04, T.76N, T.77N, T.78N and T.75E
w) After Line 1 and Line 2 conductors have been installed in T.04, T.76N, T.77N, T.78N and
T.75E, Stability Line Diff and Intertrip tests are carried out
The Use of Temporary Towers to Optimize The Completion of Reconductoring and Tower Replacement
of 150 Kv High Voltage Overhead Lines (SUTT)
656 Return: Study of Economic And Business Management, Vol 2 (7), Juuly 2023
x) Continued issuance of RLB and Energize Line 2 and Line 1 in the direction of Sukatani
Gobel.
Changes in Outage Time Duration
The duration of time under normal conditions or if reconductor work is carried out without
using a temporary tower requires a blackout time of 148 days, while if using a temporary tower,
a shorter blackout time is obtained, which requires a blackout time of 16 days. So from the results
of the analysis that has been done in this study there was a decrease of about 132 days or about -
89%.
Figure 1
Outage Time Comparison Model Between Using Temporary Tower and
Without Temporary Tower
Cost Comparison Before and After Using Tower Emergency
A significant decrease in the duration of the blackout time of 89% if the reconductor work
is carried out using temporary towers has an impact on increasing project costs. The results of the
comparison between the cost of normal conditions without using a temporary tower with the cost
to shorten the duration of the outage time if reconductoring is carried out using a temporary tower
shows that there is an additional cost. But the required duration of the outage became faster by
132 days. This means that it is still better because the additional cost of Rp. 1,872,217,454 is still
smaller than the loss received by PLN if this reconductoring work cannot be completed.
CONCLUSION
Based on the data, the results of the analysis and discussion conducted in research on one
of the Network Transmission Reconductoring projects at PT PLN (Persero) SUTT 150 kV
Sukatani New towards Sukatani, can be concluded as follows :
Comparison of the duration of the blackout time if the reconductor work is carried out
without using a temporary tower, then the blackout time of this reconductor project is 148 days.
These activities cannot be accelerated, because the system must be completely extinguished
during erection work T.04 and Uprating work of Existing Towers T.76, 77 and 78 in the direction
of Sukatani. Meanwhile, if you use a temporary tower, you get a much shorter blackout time,
which requires a blackout time of 16 days. So that from the results of the analysis that has been
done in this study there was a significant decrease of about 132 days or about -89%.
The duration of the contractual implementation time also has a faster impact if the
reconductor work is carried out using a temporary tower where if the reconductor work starts on
August 1, 2022, the work can be completed on December 26, so that the 2022 KPI target can be
The Use of Temporary Towers to Optimize The Completion of Reconductoring and Tower Replacement
of 150 Kv High Voltage Overhead Lines (SUTT)
Return: Study of Management, Economic and Bussines, Vol. 2 (7), July 2023
657
achieved. Meanwhile, if the reconductor work is carried out without using a temporary tower, the
new work can be completed on January 10, 2023, causing the KPI for 2022 not to be achieved.
Shortening the duration of the outage time if reconductor work using temporary towers
causes the project cost requirement to increase by Rp 1,872,217,454 from the original plan cost.
REFERENCES
Ahmed, U., & Saqib, M. A. (2020). Prospect of voltage uprating of a conservatively designed
EHV transmission line. Electric Power Systems Research, 182, 106203.
https://doi.org/10.1016/j.epsr.2020.106203 Google Scholar
Aldi, M., Anwar, M. S., & David, G. (2022). Company Responsibility Towards Phoneed
Employees Without Getting the Rights of Severance Pay. Return: Study of Management,
Economic and Bussines, 1(2), 6371. https://doi.org/https://doi.org/10.57096/return.v1i2.14
Google Scholar
Harefa, M. B. (2021, May 28). Kegunaan Microsoft Project Dalam Penjadwalan Proyek
Konstruksi . Anak Tekik Indonesia.
https://www.anakteknik.co.id/brilian_mei/articles/kegunaan-microsoft-project-dalam-
penjadwalan-proyek-konstruksi Google Scholar
Ines, H., & Ammar, F. Ben. (2020). Multi-criteria decision making for reconductoring overhead
lines. 2020 17th International Multi-Conference on Systems, Signals & Devices (SSD), 53
58. https://doi.org/10.1109/SSD49366.2020.9364080 Google Scholar
Kishore, T. S., & Singal, S. K. (2014). Optimal economic planning of power transmission lines:
A review. Renewable and Sustainable Energy Reviews, 39, 949974.
https://doi.org/10.1016/j.rser.2014.07.125 Google Scholar
Kopsidas, K., & Rowland, S. M. (2009). A Performance Analysis of Reconductoring an Overhead
Line Structure. IEEE Transactions on Power Delivery, 24(4), 22482256.
https://doi.org/10.1109/TPWRD.2009.2021042 Google Scholar
Krishnasamy, S. G., Ford, G. L., & Orde, C. I. (1981). Predicting the structural performance of
transmission lines uprated by reconductoring. IEEE Transactions on Power Apparatus and
Systems, 5, 22712277. Google Scholar
Maidin, R., Nurdin, M., Putera, W., Aliza, N., Qalsum, A. T. U., & Yahya, I. L. (2022).
Implementation of the Targeted Electricity Subsidy Policy at the Office of PT. PLN
(Persero) ULP Sinjai. International Journal of Public Administration and Management
Research, 8(3), 2941. Google Scholar
Mbuli, N., Xezile, R., Motsoeneng, L., Ntuli, M., & Pretorius, J.-H. (2019). A literature review
on capacity uprate of transmission lines: 2008 to 2018. Electric Power Systems Research,
170, 215221. https://doi.org/10.1016/j.epsr.2019.01.006 Google Scholar
PT PLN (Persero) Unit Induk Pusat Pengatur Beban. (2019). Kajian Kelayakan Proyek
Pembangunan GITET 500 kV Cibatu Baru II/Sukatani Beserta Outlet Terkait (Revisi ke-1)
(23.03/2019.10/132). Google Scholar
Rashmi, R., Shivashankar, G. S., & Poornima. (2017). Overview of different overhead
transmission line conductors. Materials Today: Proceedings, 4(10), 1131811324.
https://doi.org/10.1016/j.matpr.2017.09.057 Google Scholar
The Use of Temporary Towers to Optimize The Completion of Reconductoring and Tower Replacement
of 150 Kv High Voltage Overhead Lines (SUTT)
658 Return: Study of Economic And Business Management, Vol 2 (7), Juuly 2023
Reddy, B. S., & Chatterjee, D. (2016). Analysis of High Temperature Low Sag Conductors Used
for High Voltage Transmission. Energy Procedia, 90, 179184.
https://doi.org/10.1016/j.egypro.2016.11.183 Google Scholar
Reed, L., Dworkin, M., Vaishnav, P., & Morgan, M. G. (2020). Expanding Transmission
Capacity: Examples of Regulatory Paths for Five Alternative Strategies. The Electricity
Journal, 33(6), 106770. https://doi.org/10.1016/j.tej.2020.106770 Google Scholar
Riba, J.-R., Santiago Bogarra, Gómez-Pau, Á., & Moreno-Eguilaz, M. (2020). Uprating of
transmission lines by means of HTLS conductors for a sustainable growth: Challenges,
opportunities, and research needs. Renewable and Sustainable Energy Reviews, 134,
110334. https://doi.org/10.1016/j.rser.2020.110334 Google Scholar
Schweiner, R. J., Twomey, K. E., & Lindsey, K. E. (2003). Transmission line emergency
restoration philosophy at Los Angeles Department of Water and Power. 2003 IEEE 10th
International Conference on Transmission and Distribution Construction, Operation and
Live-Line Maintenance, 2003. 2003 IEEE ESMO., 1117. Google Scholar
Teniwut, M. (2022, November 28). Teknik Pengumpulan Data dan Metode Penelitia Sumber.
Humaniora. https://mediaindonesia.com/humaniora/539107/teknik-pengumpulan-data-dan-
metode-penelitian Google Scholar
Vadivel, Karthi. K. (2017). Emergency Restoration of High Voltage Transmission Lines. The
Open Civil Engineering Journal, 11(1), 778785.
https://doi.org/10.2174/1874149501711010778 Google Scholar
Wale, P. M., Jain, N. D., Godhani, N. R., Beniwal, S. R., & Mir, A. A. (2015). Planning and
Scheduling of Project using Microsoft Project (Case Study of a building in India). IOSR
Journal of Mechanical and Civil Engineering (IOSR-JMCE), 12(3), 5663.
https://doi.org/10.9790/1684-12335763 Google Scholar